October 29, 2026
Since March 2025, the Lakeside County Water and Sewer District has issued sewer capacity for 150 homes to Discovery Land, the developer behind Territory 1889. By the district's own count, room for 39 more homes is left for everyone else in Lakeside until a new treatment plant opens, and that plant isn't expected until 2028.
On October 20, the district board approved a temporary moratorium on annexing new properties, according to the Flathead Beacon. If you're comparing west-shore homes or land this winter, two parcels with the same view and a similar price can now have very different futures. One is inside the district line and one is outside it. No listing photo shows that line.
The district measures capacity in gallons per day and turns that into "equivalent dwelling units," or EDUs, at 230 gallons each. Its rules describe an equivalent user as an average single-family home. The capacity summary the Beacon published starts from a baseline of 87,703 gallons per day, set by the Montana Department of Environmental Quality as of March 28, 2025. It then subtracts every commitment made since.
| Commitment | EDUs | Status in the summary |
|---|---|---|
| Discovery Land, Phase One | 100 | Issued since March 28, 2025 |
| Discovery Land, Phase Two | 50 | Issued since March 28, 2025 |
| Steam Boat Phase 1 | 60 | Not utilized yet |
| Lakeside Estate Phase 4 | 24 | Utilized |
| Lakeside Homes | 10 | Issued since March 28, 2025 |
| Marco View-Milbrandt | 9 | Utilized |
| Lakeside Hills | 8 | Issued since March 28, 2025 |
| Angels Way Sub. | 5 | Issued since March 28, 2025 |
| Med MT LLC, 414 Blacktail Rd | 4 | Issued since March 28, 2025 |
| Wee Casa Campground / RV Park | 10,210 gal/day | Preparing for construction |
Subtract those commitments and the summary shows 67 EDUs, a figure it dates April 27, 2026. Individual hookups come off that figure too. There were 18 new EDUs in fiscal year 2025, mostly in-district Lakeside connections plus a few in Somers, and 10 so far in fiscal year 2026. That leaves 39 in total.
Those 28 units set the pace. Ordinary one-home-at-a-time connections used 28 units across FY2025 and FY2026 to date. At that pace, 39 units doesn't comfortably last until 2028. The issued but unbuilt allocations also matter. Steam Boat's 60 units and Discovery Land's 150 sit on the books as spoken for, whether or not a single foundation has been poured.
Seen that way, the moratorium is a triage decision. "Our first responsibility is to protect our commitments to the customers and property owners already within the district," General Manager Rodney Olson told the Flathead Beacon. The board's October 20 agenda lists it as Ordinance 26-3, "Temporary Moratorium on New Annexations Requiring Wastewater Treatment Capacity."
The board kept some discretion. Until the new plant comes online, it can approve annexations case by case once the needs of properties already in the district are met. Olson's examples were a lake house just outside the district that wants to come off septic, or another emergency. Whether any particular property qualifies is up to the board, so only the district can answer that for a specific parcel.
For a buyer, this changes the order of questions. Outside the boundary, a new build may have to plan around an on-site septic system. That runs through Flathead County's sewage and septic process, which starts with a Land Research Request before a new permit application. The county's application page separates site evaluations from site reviews. Site evaluations cover parcels over 20 acres without prior approval, plus replacement systems. Site reviews are usually for parcels under 20 acres that already have a Certificate of Subdivision Approval. It also notes that new development requires a non-degradation analysis. Each of those steps takes time, and the county decides the outcome, not the seller.
Being inside the district is the stronger position, but it isn't unlimited. The district's rules, Ordinance 11-2, tie original-district parcels to the capacity set in Resolution No. 33 from December 7, 1994, at one equivalent user per half acre. Anything above that counts as "expanded capacity," and so does all new out-of-district service. A large in-district parcel bought with plans to split it or add units can run into that ceiling.
Fees follow the same logic. The posted fee table, labeled effective September 1, 2023, lists a $4,162 sewer system-development fee for a ¾-inch connection, a $2,081 sewer latecomer fee for out-of-district or over-density service, and a $100 permit and inspection fee. The rules also say an existing connection can owe a plant investment fee if its use or capacity changes. Since that schedule dates from 2023, confirm the current figures with the district before relying on them.
The district's developer guide spells out the sequence. First you ask about service availability, capacity, annexation requirements and timing. A will-serve letter is issued only once requirements are met and capacity is available. If a buyer's plan depends on that letter, the answer belongs in the due-diligence window, before closing.
The orange cones on US 93 are part of the same story. The gravity sewer main being replaced from Blacktail Road to Bierney Creek Road is a $4.2 million contract awarded to Swank Enterprises. The Bigfork Eagle reported that Discovery Land is financing 100% of it under a March 2025 service agreement with the district. That section of main serves all of Lakeside and everything south of it. New 12-inch and 15-inch lines are going in.
"It's not an expense that we have to pass on to our ratepayers, but we will still get to update our system and make it significantly more reliable for future growth," Olson told the Bigfork Eagle. The deal makes sense on both sides. The district gets a 1987-era collection system rebuilt without billing customers for it. The developer gets an upgraded mainline that will serve its planned resort. Pipes and treatment are separate questions, though. A bigger main moves more wastewater, but the plant at the end of it is what sets the 39-unit limit.
The work was 75% complete as of October 21. Remaining construction and permanent asphalt were expected by the end of November, and the schedule could change. Chip seal on the replaced pavement is planned for early 2027. Check MDT's construction report for current lane closures before you drive through.
The 2028 date depends on several decisions still in motion.
Can a property outside the district still get sewer before 2028? The board can approve annexations case by case once existing-district needs are met. Its stated examples were a lake house coming off septic or an emergency. Only the district can say whether a specific property qualifies.
Does the moratorium affect homes already connected? It targets new annexations. Changing an existing connection's use or capacity can still trigger fees under the district's rules.
When will the new plant be ready? The district expects 2028. That timeline sits alongside pending litigation and cost estimates that don't match.
This post is general information, not legal, tax or financial advice. Confirm your own parcel's situation with the district, the county and the right professional before you act.
If you're looking at a Lakeside lot or a home with plans attached, let's find out which side of the district line it sits on before you write the offer. I'll help you get the right questions to the right offices while there's still time to use the answers. Maureen Gerber. Let's Connect.
Stay up to date on the latest real estate trends.
Choosing the right real estate professional makes all the difference when buying or selling in Whitefish. Clients receive expert guidance, strong market knowledge, and a proactive, detail-driven approach designed to make every transaction seamless and strategic. Whether purchasing a first home, searching for a mountain retreat, securing an investment property, or preparing to list, each step is handled with clear communication, skilled negotiation, and a deep understanding of property value and craftsmanship. With a commitment to protecting clients’ interests and delivering results, the focus is always on helping you find not just the right property, but the right place to belong—so you can truly live where you love and love where you live.